PLAIN CEMENT CONCRETE
PLAIN CEMENT CONCRETE
1. OBJECTIVE:
The objective of this method statement is to
carry out the PCC works by meeting the technical specification and complying
with Standards.
2. SCOPE:
The scope of this method statement includes at
all areas at CTSIL, CTSIL site while executing it in accordance with Technical
specifications.
3. REFERENCE
4. TOOLSAND TACKLES
5. MATERIAL USED:
· Concrete Mix as per site requirement
6. PROCEDURE:
a) General:
· Ensure Material approval prior to start work
· Ensure cleaning to be done properly.
· Ensure proper surface preparation.
· Ensure Floor protection of Concreting area.
· Ensure necessary safety precautions are in place prior to start.
b) Sequence of Work:
· Ensure the footing Measurement Length, breadth and Depth.
· Ensure sawdust, chips and other construction debris shall be removed.
· Ensure anti-termite treatment is done.
· Bull mark or Level pegs should be fixed on edges and centre of footing with required top level.
· PCC M15 Grade should be used from RMC/Site Mix.
· Concrete by vision should be homogenous and proper level.
· If formwork required provide at the edge.
· Poured surface to be rammed and finished smoothly
7. RESPONSIBILITIES.
· Construction Manager: He shall be responsible for overall management of construction activities.